Highway concessionaire PLUS Malaysia has announced that the construction of Package 1 of the Juru–Sungai Dua traffic dispersal project has now reached an overall progress of 54.61% as of November 8, up from the 34.6% it was at in August. This keeps the project well on track to meet its schedule of being operational by the end of 2027, in line with its 24-month construction period.

The scope of Package 1 includes improvement works on the slip roads at the East-West interchange roundabout as well as the construction of a new bridge along Jalan Tun Hussein Onn, which is targeted at increasing road capacity and help ease congestion in the area.

In a statement, PLUS reiterated that the implementation of subsequent packages will be done in stages, with Packages 2 and 5 currently in the final stages of the tender process.