Works Minister Alexander Nanta Linggi attributed delays in the Sabah Pan Borneo Highway project to changes in its implementation model, the Covid-19 pandemic, land acquisition and utility issues, and contractor performance.
His explanation came after the Auditor-General’s Report highlighted prolonged delays and weaknesses in the project, resulting in 706km still being under construction for more than a decade...
His explanation came after the Auditor-General’s Report highlighted prolonged delays and weaknesses in the project, resulting in 706km still being under construction for more than a decade.
According to Nanta (above), the change from the Project Delivery Partner (PDP) model to a conventional procurement method in 2019 was among the factors that delayed the project.
%2Ffile%2Fattachments%2Forphans%2FWorksMinisterAlexanderNantaLinggiinparliament081026111_282538.png&w=900&output=webp&q=85&we)
%2Ffile%2Fattachments%2Forphans%2Fhaze1_212661.png&w=480&output=webp&q=85&we)
%2Ffile%2Fpublisher-c1a3f893382d2b2f8a9aa22a654d9c97%2F2020%2F03%2F9183ac91e5986a241190a19c316d0dcb.jpg&w=480&output=webp&q=85&we)
%2Ffile%2Fattachments%2Forphans%2Fconfirm11_129293.png&w=480&output=webp&q=85&we)
%2Ffile%2Fattachments%2Forphans%2FIsmailLasim1_883710.png&w=480&output=webp&q=85&we)
%2Ffile%2Fattachments%2Forphans%2FPart2_789843.jpg&w=480&output=webp&q=85&we)
%2Ffile%2Fattachments%2Forphans%2F833780259_4724541361094021_8978085125395698854_n_142428.jpg&w=480&output=webp&q=85&we)