KUCHING, Oct 17: The road project linking Sejingkat Bridge to the new route leading to Batang Samarahan Bridge is progressing according to schedule and is expected to be completed in the third quarter of 2027.
Public Works Department (JKR) Sarawak director Datu Ir Cassidy Morris inspected the project site to assess the progress of construction works today.
Cassidy (third left) during a visit to road project site linking Sejingkat Bridge to Batang Samarahan Bridge on Oct 17, 2026. Photo: JKR Sarawak In a post shared on its social media, JKR Sarawak said the project involves the construction of approximately 6.3km of road to JKR R5 standards, featuring a two-way undivided carriageway, two signalised intersections and minor junctions.