PENAMPANG, Oct 30 — Two rural road upgrade projects in Kampung Buayan and Kampung Terian here, involving a total allocation of RM173.263 million, are making positive progress, with both projects ahead of their scheduled completion timelines.
Sabah deputy chief minister III Datuk Ewon Benedick said the RM73.868 million Kampung Buayan rural road upgrade — involving a 5.6-kilometre stretch of road and the construction of two bridges — is at 76.64 per cent physical progress, 45 days ahead of schedule, and is expected to be completed in August 2027, while the RM99.395 million Kampung Terian rural road upgrade — involves a 6.7-kilometre stretch of road — is at 57.83 per cent progress, 58 days ahead of schedule, and is expected to be completed in May 2028.