PENAMPANG, Oct 30 (Bernama) -- Two rural road upgrade projects in Kampung Buayan and Kampung Terian here, involving a total allocation of RM173.263 million, are making positive progress, with both projects ahead of their scheduled completion timelines.
Two Rural Road Upgrade Projects In Penampang Ahead Of Schedule - Ewon
Sabah, Ewon Benedick, rural road upgrading, Pena
Key takeaways
Two rural road projects in Penampang are ahead of schedule, with funding from the federal government.
- Kampung Buayan project is 76.64% complete, 45 days ahead of schedule, expected completion in August 2027.
- Kampung Terian project is 57.83% complete, 58 days ahead of schedule, expected completion in May 2028.
- Projects are monitored by Sabah Public Works Department and funded by the Rural and Regional Development Ministry.
Summarised automatically by AI from the original article by Bernama. AI can make mistakes, so check the original for details.
Story details
- Published
- Section
- news
- Format
- Article
- Original
- bernama.com ↗
Related reporting
6 stories on this topic from 5 sources, oldest first.
- Free Malaysia Today Rural road projects in Sabah, S’wak not cancelled by federal govt
- Free Malaysia Today Don’t mislead public over rural road projects, PKR tells Umno
- Bernama Two Rural Road Upgrade Projects In Penampang Ahead Of Schedule - Ewon (this story)