GUA MUSANG, Oct 18 (Bernama) -- The installation of a Bailey bridge on the FT008 Gua Musang-Kota Bharu Federal Road, which was closed due to a sinkhole, is expected to be completed by Oct 24, subject to weather conditions and smooth work progress.
General : Bailey Bridge Installation On Gua Musang-Kota Bharu Road Expected Ready On Oct 24
JKR, Bailey bridge, installation
Key takeaways
A Bailey bridge installation on the Gua Musang-Kota Bharu road is expected to be ready by Oct 24, with 40% completed so far.
- The bridge is 40% complete, with 40 feet installed out of 140 feet.
- Construction of approach roads will start after the main structure is in place.
- The project involves 34 JKR personnel and faces minor rain-related challenges.
Summarised automatically by AI from the original article by Bernama. AI can make mistakes, so check the original for details.
Story details
- Published
- Section
- news
- Format
- Article
- Original
- bernama.com ↗
Related reporting
6 stories on this topic from 6 sources, oldest first.
- Bernama General : Bailey Bridge Installation On Gua Musang-Kota Bharu Road Expected Ready On Oct 24 (this story)


%2Ffile%2Fattachments%2Forphans%2FSaifuddinNasutionIsmailasdfvsd_373863.png&w=480&output=webp&q=85&we)