SEPANG, Nov 1 — One of two flood bank strengthening sites in Kampung Rancangan Tanah Belia (RTB) Bukit Changgang here is 80 per cent complete and is expected to be finished next week, ahead of its original January 2027 deadline.
The project, undertaken by the Department of Irrigation and Drainage (JPS), uses the Schematic Precast System (SPS) to reinforce an existing earth embankment that is frequently eroded by strong currents in Sungai Langat.
Universal Precast System project engineer Luqman Hakim Omar said work on the project, which began on September 23, was in its final phase, with the remaining 20 per cent, including concreting, expected to be completed by this weekend before the site is handed over to JPS next week.