TEBEDU, Nov 16: Some 3,000 residents across seven villages are expected to benefit from improved road connectivity when the RM48.188 million Temong–Tepoi/Sadir Phase 2 road project is completed in November 2027.
Sarawak Public Works Department (JKR) director Datu Cassidy Morris said the project, which stretches about 7.4 kilometres from Kampung Temong to Kampung Tepoi, has achieved 24 per cent physical progress, ahead of its scheduled progress of 21.43 per cent.
The project comprises 6.64 kilometres of new paved main road and a 0.73-kilometre connecting road to nearby villages, according to the Sarawak Public Communication Unit (UKAS).
Fully funded by the Sarawak government, the project is expected to improve access for residents of Kampung Temong Bengan, Kampung Temong Putah, Kampung Temong Mura, Kampung Temong Mawang, Kampung Darul Falah, Kampung Darul Huda and Kampung Tepoi.