KUCHING, Nov 3: A total of 38 out of 880 ongoing construction projects nationwide have been classified as sick projects as of Oct 31, involving a current project cost of RM2.080 billion.

According to Works Minister Dato Sri Alexander Nanta Linggi, 77 per cent of the project delays were attributed to weaknesses in contractors’ management, including poor work planning and coordination at construction sites, insufficient manpower, and issues involving machinery and construction material supplies.

The remaining 23 per cent were caused by other factors, including utility relocation, land acquisition, limited site access, constraints in construction material supplies, rising diesel prices, and technical issues.