KUALA LUMPUR: Jati Tinggi Group Bhd's wholly owned subsidiary, Jati Tinggi Holding Sdn Bhd, has secured a RM33.09 million contract for power infrastructure works to support a data centre in Gerbil, Negeri Sembilan.

In a Bursa Malaysia filing today, it said the contract involves the supply, design, installation, testing and commissioning of two circuits of 275 kilovolt power cables connecting the transition yard to the data centre substation.

It also covers the construction of a transition yard, overhead line T-off works and related secondary system modifications to support the data centre's interim power supply infrastructure requirements.

"The contract shall be for a period of nine months effective from the notice to start work," it said.