KUDAT, Oct 18 (Bernama) -- The 11.4 per cent completion rate for the Sabah Pan Borneo Highway project highlighted in the recent Auditor-General's Report does not reflect the actual physical progress on the ground, says Deputy Chief Minister Datuk Seri Dr Joachim Gunsalam.
General : 11.4 Per Cent Figure Does Not Reflect Actual Progress Of Sabah Pan Borneo Highway - Dr Joachim
Joachim Gunsalam, Pan Borneo, JKR Sabah, Auditor-G
Key takeaways
Dr Joachim says the 11.4% completion rate for Sabah's highway project doesn't reflect actual progress, as many packages are still under construction.
- The 11.4% figure only counts handed-over packages, not overall progress.
- Some highway sections have 90-93% physical progress, according to the minister.
- Variation orders for the project are approved by federal ministries, not the state government.
Summarised automatically by AI from the original article by Bernama. AI can make mistakes, so check the original for details.
Story details
- Published
- Section
- news
- Format
- Article
- Original
- bernama.com ↗
Related reporting
3 stories on this topic from 3 sources, oldest first.
- Bernama General : 11.4 Per Cent Figure Does Not Reflect Actual Progress Of Sabah Pan Borneo Highway - Dr Joachim (this story)

%2Ffile%2Fattachments%2Forphans%2FSaifuddinNasutionIsmailasdfvsd_373863.png&w=480&output=webp&q=85&we)