KUALA LUMPUR, Nov 17 — The government could face legal action and damage claims if it arbitrarily terminates contracts awarded to contractors for the Sabah Pan Borneo Highway (LPB) project without following established procedures and legal requirements.
Works Minister Datuk Seri Alexander Nanta Linggi said contract termination was not a decision that could be taken lightly, as contractors had legal rights, including the right to apply for an Extension of Time (EOT) if project delays were caused by factors beyond their control.
These include delays in site handovers arising from the government’s failure to finalise compensation payments for land acquisition.
“If the (state) Department of Lands and Surveys has not settled land acquisition compensation, contractors cannot access the site because landowners will not allow them to do so. In such cases, they are indeed entitled to claim an extension of time.