KUCHING, Nov 18: The Ministry of Works has taken a firm stance against the issue of delays in rural educational building infrastructure in Sarawak by imposing fines and contract termination notices on contractors of four school projects categorised as delayed (sick) projects.
Deputy Minister of Works Datuk Seri Ahmad Maslan stated that the four school projects involve Sekolah Menengah Kebangsaan (SMK) Tinjar in Baram, Sekolah Kebangsaan (SK) Sebat in Lundu, SMK Belaga, and SK Abang Leman in Saratok, each experiencing project delays of between 18 and 33 per cent.
“For example, at SK Abang Leman – which involves the construction of classrooms, a full replacement of 30 classrooms, a hostel for 600 students, and 12 units of teachers’ quarters – we issued a notice for contract termination to the contractor on November 10.