KUALA LUMPUR, Oct 26 (Bernama) -- The permanent disposal facility (PDF) for radioactive waste generated by Lynas Malaysia Sdn Bhd had achieved 77 per cent completion in construction and operations as of Aug 31, with 1.45 million metric tonnes of the 1.467 million metric tonnes of Water Leach Purification (WLP) waste generated having been transferred to the facility.
General : Lynas Radioactive Waste Disposal Facility 77 Pct Complete As Of Aug 31
Chang Lih Kang, Lynas, permanent disposal facility
Key takeaways
Lynas' radioactive waste disposal facility is 77% complete, with most waste transferred, and radiation levels remain below limits.
- 77% of Lynas' radioactive waste facility is complete as of Aug 31.
- 1.45 million tonnes of waste have been transferred to the facility.
- Radiation levels outside the facility are below legal limits.
Summarised automatically by AI from the original article by Bernama. AI can make mistakes, so check the original for details.
Story details
- Published
- Section
- news
- Format
- Article
- Original
- bernama.com ↗
Related reporting
2 stories on this topic from 2 sources, oldest first.
- Bernama General : Lynas Radioactive Waste Disposal Facility 77 Pct Complete As Of Aug 31 (this story)