The LCS project was 7.55% behind schedule across all five ships, while LCS 1 was 13.88%, or 108 days, behind in equipment, construction, trial and commissioning work.

PETALING JAYA: The navy's first littoral combat ship (LCS 1) could be handed over unarmed and might not be fully operational until December 2035, the national audit department says.

According to the Auditor-General’s Report 2/2026 released today, trials and commissioning could not be completed on schedule, with five complementary contracts for weapons and support systems still incomplete.

"If LCS 1 is handed over on Aug 26, 2026 or Dec 26, 2026, the ship will be delivered without complete training and weapon systems," the department said, referring to the initial date of handover and the revised target.