BENTONG: The Narcotics Addiction Rehabilitation Centre (Puspen) in Karak has been completed at a cost of RM72.1 million, up from its initial RM68.8 million.
Works Minister Datuk Seri Alexander Nanta Linggi said the project, which began in August 2021, was initially scheduled for completion on Aug 1, 2024.
However, it was only completed in July this year.
"The project faced technical and operational challenges. However, it was successfully completed through continuous monitoring and close cooperation among all parties.
"The initial cost was RM68.8 million, but increased to RM72.1 million upon completion.