After a two-year suspension in its development following a Malaysian anti-corruption commission (MACC) investigation into alleged irregularities and earthwork expenditures, the long-delayed Sungai Petani racing circuit project is again back on track, with the construction of its initial development phase, now at 78% progress, set to be completed by the middle of next year, Bernama reports.

This was revealed by Kedah MB Datuk Seri Muhammad Sanusi Md Nor, who said the initial RM16 million phase, covering infrastructure works, car park facilities and a drag racing circuit, was slated for completion by June 2027.

Speaking at the state assembly sitting earlier today, he said the project had been delayed because it had been suspended from August 2023 to August 2025 following a MACC investigation, before a decision of No Further Action (NFA) was issued for it. He said this in response to questions posed by Teh Swee Leong (DAP-Kota Darul Aman), who asked about the project’s implementation timeline, physical progress and expenditure since its inception.