KUALA LUMPUR, Oct 8 — Lumut Naval Shipyard (Lunas), the company building Malaysia’s first Littoral Combat Ship (LCS 1), has set April 2027 as the new delivery date for the vessel to the Ministry of Defence (Mindef) under Phase 1.

Defence Minister Datuk Seri Mohamed Khaled Nordin said Lunas had previously been unable to commit to or guarantee delivery by December this year.

“The delay will affect the readiness of the Malaysian Armed Forces and national defence.

“As the buyer, the ministry expects the LCS to be delivered. With the new date set for April 2027, we hope Lunas will have no further excuses or delays,” he said when winding up the debate on the Auditor-General’s Report (LKAN) No. 2/2026 for the ministry in the Dewan Rakyat yesterday.