Works Minister Nanta Linggi says arbitrary termination of Sabah Pan Borneo Highway contracts could expose the government to court action and damage claims.
KUALA LUMPUR: The government could face legal action and damage claims if it arbitrarily terminates contracts awarded to contractors for the Sabah Pan Borneo Highway (LPB) project without following established procedures and legal requirements.
Works Minister Datuk Seri Alexander Nanta Linggi said contract termination was not a decision that could be taken lightly, as contractors had legal rights, including the right to apply for an Extension of Time (EOT) if project delays were caused by factors beyond their control.
These include delays in site handovers arising from the government’s failure to finalise compensation payments for land acquisition.