Despite prolonged delays, the government said it cannot arbitrarily terminate contracts awarded to contractors for the Sabah Pan Borneo Highway project without following established procedures and legal requirements, as doing so could bring about legal action and damage claims.
According to works minister Datuk Seri Alexander Nanta Linggi, contract termination was not a decision that can be taken lightly, as contractors had legal rights, including the right to apply for an extension of time (EOT) if project delays were caused by factors beyond their control. These include delays in site handovers arising from the government’s failure to finalise compensation payments for land acquisition, Bernama reports.